Your Software Company got a project from the sale company for the development of the website to manage their visitors. They also want to k...

Responsibility assignment matrix

Your Software Company got a project from the sale company for the development of the website to manage their visitors. They also want to keep track of their frequent visitors for sales follow up. A small team which consists of website manager, web developer, content administrator, web administrator and sales manager will develop and manage this project. the activities that you perform are Project planning, Website construction, Content review, Usability testing, Installation of tracking software, Ongoing review of visitors and Sales follow up to frequent users respectively. Following are the given scale that you will use:
R=Responsible, C=Consulted, A=Accountable, I=Informed.
You have to create a responsibility assignment matrix by using the above scale, task and development team. In simple words you have to map the work of the project to the peoples responsible for performing that work using the given scale.

Answer

·         Team for this project consists
o   Website manager
o   Web developer
o   Content administrator
o   Web administrator
o   Sales manager will develop and manage this project.

·         The activities to be perform are 
o   Project planning
o   Website construction
o   Content review
o   Usability testing
o   Installation of tracking software
o   Ongoing review of visitors
o   Sales follow up to frequent users respectively.

 Following are the given scale that you will use

  • Responsibility = role is responsible for actually doing or completing the item
  • Accountable = role is accountable for ensuring that the item is completed. Usually only one person.
  • Consulted = role whose subject matter expertise is required in order to complete the item
  • Informed = role that needs to be kept informed of the status of item completion